Delta Lithium ($DLI)’s 17 November Mt Ida scoping study forecasts 640,000 tonnes of spodumene concentrate and 1.08 million tonnes of lepidolite concentrate over the modelled life. The latter contains lithium and rubidium. A reader assessing the project needs to understand both products before treating it as a conventional single-product lithium development. Study, tables 1 and 17.

The headline A$748 million post-tax NPV at 8% is an unlevered project-model result from an assumed investment-decision date. The study has ±40% accuracy, cannot support an Ore Reserve estimate and includes Inferred material. It also excludes the cost of progressing to that investment decision. Those qualifications govern how much confidence the number deserves. Pages 1–2 and 5.

The concentrates have different grades and markets

The proposed flotation plant produces 5.5% Li₂O spodumene concentrate, 3% Li₂O lepidolite containing 1.8% Rb₂O, and a separate tantalum concentrate. These are forecast product grades and quantities, not shipments already made. Pages 1 and 36.

For lepidolite, the model adjusts a spodumene reference price for grade and applies 85% payability, then adds a rubidium credit. Delta acknowledges that higher-grade lepidolite lacks a single common pricing formula and that its potential customer base is smaller than spodumene’s. The adopted formula is consequently an assumption to test with customers. Pages 45–46.

Table 17 specifies a US$671 per tonne rubidium credit added to LC3.0 concentrate. The detailed discussion refers to downstream processing costs and potential bulk industrial use of rubidium formate, alongside a comparison with a high-purity rubidium carbonate quotation. These are different product stages. The chemical quotation cannot simply be applied to rubidium oxide in the ground. Pages 46–47.

Delta says a more substantive rubidium marketing study and further customer discussions will address the assumptions in the next phase. We would give agreed specifications, recoveries and commercial payability more weight than a comparison between the quoted prices of different chemicals. That does not establish that the credit is unattainable; it identifies what the next study needs to demonstrate.

The funding requirement extends beyond the capital headline

Pre-production capital is A$483 million including contingency. The financial evaluation estimates approximately A$498 million peak negative cash flow, with later funding discussion rounding the requirement to about A$500 million. These are different model scopes, rather than three amounts to add together. Pages 6, 47 and 49.

The disclosed US$756/t operating cost is calculated over the combined spodumene and lepidolite concentrate tonnage and excludes royalties. It is not an SC6-equivalent cost that can be subtracted from any lithium benchmark to derive a mine margin. Pages 6 and 45.

The constructive evidence is a defined resource, metallurgical work and a proposed process that recovers several products. Further engineering could improve the economics, and the company identifies financing and partnership options. Against that, funding, product marketing and higher-confidence studies remain ahead. Agreed product terms and a higher-confidence mine plan would make the next result more persuasive.